Monday, May 7, 2012

[ParamountGroup] Orchid current status update / possession letter / Open Meeting date proposal

 

Dear All

I have flat in Orchid (#3012) ,I have visited tower yesterday till 5th floor and below are the updates:
1. Tower is interior work like Tiles, wiring etc is completed for most of flats (some 2 BHK are still pending for bathroom tiles etc)
2. Bedroom wood work is not done ,I think it would be last.
3. Doors are installed but glass work is pending
4. They have created a iron rod boundary around tower & Tower outside construction is on the way (May be outside floor)
5. Ground floor is still mess & you still have iron ROD support all around ,white wash is not done on 2 BHK not sure why
6. Have was lift space but can't trace any installation
7. Talk to few worker or supervisor ,they seems to positive about completing interior work in next two month
8. Mapple basic is structure is half done

I also received possession letter today , have not studied fully yet but just wanted to know what unit remaining price means in payment details & by when Parking money need to be paid.

I suggest to have meeting on coming Saturday and request Maps to help! Anyone want to have any discussion can call me @9953944657. We need to be united & more communicative otherwise builder will force us whatever he want .

Thanks,
Naresh

__._,_.___
Recent Activity:
.

__,_._,___

No comments:

Post a Comment