Re: [ParamountGroup] Orchid flat registration

 

So are you ready to forgo the penalty for may, jun, july, aug month?

regards
Vipin

On 5 Sep 2012 14:17, "Ashish Chandra Gupta" <ashishchandra.gupta@gmail.com> wrote:
 

they calculate @ 18 % per annum 


Regards
Ashish

On Wed, Sep 5, 2012 at 8:58 AM, Vipin Madaan <madaan.vipin@gmail.com> wrote:
 

Can someone explain how paramount calculate interrst charges. I had a delayed payment due to delay in bank disbursement of 11.5lac. Duration of delay is 4months.

Paramount has instead of paying me penalty has put 4000 as remaining interest on me. Should they not be paying penalty from oct2011 to sep 2012? Considering a grace period of 3 months.

On 3 Sep 2012 13:02, "Nirmesh Mangal" <nirmesh.mangal@yahoo.com> wrote:
 

Hi Atul,
I've received a penalty from december,11 to march,12 as my two months penalty i.e. of oct & nov got adjusted in interest because of delay payment & very soon they will give the penalty for the month of april too. apart from registry charges we need to give a 10,000/- cheque on the name of admin. charges which paramount is saying is for lawyer fees & several other charges.


From: atul jain <jainatul_chd@yahoo.com>
To: ParamountGroup@yahoogroups.com
Sent: Monday, 3 September 2012 10:38 AM
Subject: [ParamountGroup] Orchid flat registration

 
Dear Orchid Allotees,
Kindly inform on the following issues:
1. Chowkidarana charges payable to Paramount from which date in the case of non registration of sale deed of flat?
2. Payment of penalty by Paramount where due date of possession was 30/6/2011 as per allotment letter issued byParamount.
3.Amount payable on account of stamp charges, advocate fees and other legal charges in case of A1 type(1700 sq. ft) flats.
 
with regards
Atul Jain
09915586922