Saturday, August 18, 2012

[ParamountGroup] Re: Possession letter details

 

hi,
I have gone through a personal vist with my friends and found that they have done a quite impressive work in last 2 months.Their 1 lift is in working order & for the second they are giving the deadline of aug end.for rest of the work like paint & final fittings & all they are asking 25-30 days after registry.seems they reached in position for that.

let's hope for the good

--- In ParamountGroup@yahoogroups.com, ravi jain <ravijain2k@...> wrote:
>
> paramount.del@..., dev.oct286@...
>
> --- On Mon, 1/8/11, Manish Sharma <manish13sharma@...> wrote:
>
>
> From: Manish Sharma <manish13sharma@...>
> Subject: Re: [ParamountGroup] Possession letter details
> To: ParamountGroup@yahoogroups.com
> Date: Monday, 1 August, 2011, 2:34 AM
>
>
>  
>
>
>
>
> which email id you are using to correspond with them? They never seem to even repy to my email/call me back.
>  
> Regards,
> Manish
> Soliaire
>
>
> On Sun, Jul 31, 2011 at 2:56 PM, ravi jain <ravijain2k@...> wrote:
>
>
>  
>
>
>
>
>
>
>
>
> guys
> I have been trying to get paramount commit to date of possession letter and the penalty check.
> Not sure how you guys are dealing with them, but I have been trying to do this via email.
> Every email/reminder sent is responded by a call from one of there representative with unclear thought process everytime.
> And when I ask them to confrim in writing, I am told its not there policy to do email replies.
> can any of you faces similar situation?
> I am thinking to send them a registered/sped post hard copy shortly, any suggestions?
> Pls let me know ..
>  
> Also, as stated in this thread, is there any legal writeup/document by law which defines the pre-requisute for a builder to generate the possession letter?
>  
> Regards
> Ravi
> Symphony
>
> --- On Sun, 31/7/11, ashish sharma <ashish_sharma7@...> wrote:
>
>
> From: ashish sharma <ashish_sharma7@...>
>
> Subject: Re: [ParamountGroup] Possession letter details
> To: ParamountGroup@yahoogroups.com
>
> Cc: "ParamountGroup@yahoogroups.com" <ParamountGroup@yahoogroups.com>
> Date: Sunday, 31 July, 2011, 11:02 PM
>
>
>
>
>
>  
>
>
>
> Not only Paramount, all other builders are charging in the same range.
>
>
> There will be no resolution of this one sided affair unless we all (not the MAPS representatives only) meet the builder and have a talk face to face. 
>
>
> If the builder has offered possession, then there must be the completion certificates ready with him. Let us start asking them from the builder and then all the actual facts will start coming out. 
>
>
> I will want to attend a meeting with the builder along with all the effected owners of Paramount Symphony.
>
>
> This drama from builder was bound to happen near the time of possession. Exactly same situation came when Crossing Infra started offering their appts. Unfortunately nothing happened after so many heated meetings with the management. All the charges remained same and the owners are paying the charges for incomplete society. .......
>
>
> This will happen to all Paramount members as well if we do not come to the table and start talking with the management.
>
>
> Ashish
>
>
>
>
>
> From: Jitin Arora <JITINA@...>
> To: "ParamountGroup@yahoogroups.com" <ParamountGroup@yahoogroups.com>
> Cc: "ParamountGroup@yahoogroups.com" <ParamountGroup@yahoogroups.com>
> Sent: Sun, 31 July, 2011 8:17:35 PM
> Subject: Re: [ParamountGroup] Possession letter details
>
>  
>
>
> and there will be recurring charges per month to use the club house also. 
>
>
> We should not pay final 5% unless house is ready go move in. 
> Also should get all these recurring charges reduced to practical range. 
>
>
> Paramount is charging excessively for these facilities. 
>
>
> Thanks
>
> ~ Jitin
>
> On Jul 31, 2011, at 3:07 AM, Ashish Chandra Gupta <ashishchandra.gupta@...> wrote:
>
>
>
>
>  
>
> We should not even accept the possession letter without the basic clearance from the various departments, by doing this they want to save there penalty  !
>
>
> Ashish
>
>
> On Sat, Jul 30, 2011 at 9:49 PM, Jitin Arora <JITINA@...> wrote:
>
>
>  
>
>
>
> Hi Friends,
>
> Main highlights of the possession letter from Paramount :
>
> a. Pay all dues, get NOC from fianance dept.
> b. Get registry done and provide details to them
> c. They will take 25-30 days then to give actual possession of apartment. Advised to complete before Dec 1 2011.
>
>
> Recurring Cost :
>
> 1. Rs 1.20 / sq. ft building maintenance charges.
> 2. Rs 0.30 / sq. ft township maintanance charges.
>             So, that's total 1.50 / sq. ft which means approx Rs 1600 (2 BR) to Rs 2700 (3BR + SQ) PER MONTH
> 3. 100 / kwt per month Power backup charges.
> 4.  65 / kwt per month electricity charges.
>             So, avg 3 Kwt house will pay FIXED COST Rs. 485 PER MONTH + actual usage cost
> 5. Effective 1/12/2011, if you do not take possession you have to pay Chowkidana charges of 150 per day !! That's INR 4500 per month - insane !
>
> They are not only charging FIXED INT. FREE MAINTENANCE, ELECTRICITY, POWER BACKUP, FIRE FIGHTING, CLUB HOUSE charges but also the above mentioned RECURRING CHARGES.
>
> I feel the maintenance charges and electricity charges are way too high. We should compare it with adjoining areas of Indirapuram, Noida Ext and Noida.
>
> Thanks
> Jitin Arora
>
> Email: jitin.a@...
>
>
>
> On Fri, Jul 29, 2011 at 4:07 AM, gopalkrishna_m <gopalkrishna_m@...> wrote:
>
>
>  
>
>
>
> I visited to PARAMOUNT site today morning and it would take atleast 3-4 months to complete the major work. Below are some points which are still pending ..
>
> 1. Boundary wall ( Not Started yet )
>
> 2. Entrance gate ( Under Construction , will take atleast 2 months )
>
> 3. Parking Area ( under construction )
>
> 4. Lights ( Not started yet, No Pillar, NO lights in parking Area )
>
> 5. Common Area ( under Construction )
>
> 6. Security ( We should have clear visibility on this )
>
> 7. Power Backup
>
> Rgds,
> Gopal
>
>
> --- In ParamountGroup@yahoogroups.com, Jitin Arora <JITINA@> wrote:
> >
> > this is very true.. we have seen builder go back on so many promises..
> > when we have waited so long let's make sure we are getting our dream house
> > in livable condition.
> >
> > its prudent to let him finish the apt., get all clearances and then only
> > take possession.
> > Final 5% must be paid only when its READY to move in. I think registry can
> > be done before that, there is no rule which says registry has to be done
> > when apt. is ready, but we should not pay builder full amt before he shows
> > us the complete ready apartment.
> >
> > Thanks
> > Jitin Arora
> >
> > Email: jitin.a@
>
> >
> >
> > On Thu, Jul 28, 2011 at 11:34 PM, vikas mehrotra
> > <Vikas_meh@>wrote:
>
>
>
> >
> > > **
> > >
> > >
> > > I have also seen the TV report of Supertech case. There was a report on TV
> > > last week that builders ( specifically named Supertech but the coverage was
> > > for entire crossing republik) are handing over half build societies to the
> > > buyers even before acquiring completion certificates and other NOCs from
> > > government authorities. Even the case of mahagun was reported that the
> > > Fire safety deptt has not cleared the towers still the possession letter
> > > were issued.
> > >
> > > It is a serious issue and has to be dealt with equal serious ness from our
> > > side. We cannot risk our's and our family's lives by hurriedly takling
> > > possession without verifying the actual facts of completion.
> > >
> > > No buyer is denying to pay the balance amount now. infact all wanted to
> > > have the possession at the earliest but without compromising on safety. Need
> > > to take up the matter with the builder as was done by crossing flat owners
> > > when they were issued possession letter (draft of letter attached ).
> > >
> > > This is my personal view . Though I have not received possession offer
> > > letter yet but I would definately send this letter before making the final
> > > payment and then would proceed for possession formalties after getting the
> > > satisfactory reply from the builder.
> > >
> > > What can you do if all the payment has been made but the builder could not
> > > complete the flat or get the neccessary clearances in next two-three months
> > > from the authorities...
> > >
> > > Play safe...
> > >
> > > Regards
> > >
> > > Vikas Mehrotra
> > > Yantra 1405
> > >
> > >
> > > From: "tushar_saxn" <tushar.saxna@>
>
> > > Sent: Thu, 28 Jul 2011 19:42:13
> > > To: ParamountGroup@yahoogroups.com
> > > Subject: [ParamountGroup] Possession letter by builder without completion
> > > !!
> > >
> > >
> > > IMP INFORMATION !!!
> > >
> > > I have been following up with the yahoo groups of other builders ..
> > > and they are doing the same...giving possesion letters without completing
> > > the building...to avoid penalty checks,.,
> > > even a person in mahagun contacted Media and this complete story was shown
> > > on some new channel...
> > > some hint of the same is happening in supertech as well...
> > > so we need to understand is it that builder just faking us to avoid penalty
> > > checks or is that the building is actually ready for possession...
> > >
> > > I strongly feel that we need MAPS to be reunited again !!
> > >
> > >
> > >
> > > <http://sigads.rediff.com/RealMedia/ads/click_nx.ads/www.rediffmail.com/signatureline.htm@Middle?>
>
> > > Treat yourself at a restaurant, spa, resort and much more with *Rediff
> > > Deal ho jaye!<http://track.rediff.com/click?url=___http://dealhojaye.rediff.com?sc_cid=mailsignature___&cmp=signature&lnk=rediffmailsignature&newservice=deals>
> > > *
> > >
> > >
> > >
> >
>